Hi,
I need to have a validation coding mask when WBS under project definition must be same with project definition.
For example :
Project Definition : ABCD3PLH
WBS level 1 : ABCD3PLH1
WBS level 2 : ABCD3PLH2
WBS level 3 : ABCD3PLH3
I need validation to validate the first 4 character which ABCD.
What should i do in Validation (OPSI). Should i maintain in PRoject definition or WBS element ?
Plz help.
Cheers,
Nies
Prerequisite
PROJ-PROFL = 'ZXY'
Check
PRPS-POSID : 1-8 := PROJ-PSPID : 1-8:
Warning:
WBS code not matching to definition
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.