How to set a default target system in a change request

Former Member
0 Kudos

Hello,

I would like to set up a default value for the target system when I create a change request,

for example, if I create a CHR in "DEV" system, it would auto fill the "Target" field with "TST"

I tried to look for TPPARAM parameters or some Global ones,

but with no luck

Anyone got a clue how to do it?

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

debasissahoo
Active Contributor
0 Kudos

Hi Elhanan,

The next system depends on the transport route.

and the transport will follow the route assigned. this again depends on the transport layer assinged to the development package of the object.

so the assignment is like this.

Dev object > Development package (previously called dev class) > Transport layer > Transport Route

for more information, please see the help.sap.com software logistics part.

http://help.sap.com/saphelp_nw04/helpdata/en/60/e3fcfae36811d184810000e8a57770/frameset.htm

Hope this helps,

Debasis.

Former Member
0 Kudos

Hi ,

The link above is not working . Any other  link you have for solution..

Thanks

Arundhati

Answers (2)

Answers (2)

Former Member
0 Kudos

I had similar problem..

after my development system refresh any changes on the Z package(zgsd) related objects were created locally..

this was due to Development system refresh..

to resolve this issue i have created ZGSD layer in stms->over view->transport routs-.edit-> transportlayer->create

here i had to create ZGSD package..as my dev system was refreshed. and then distribute the configuration...

my issue has been resolved by doing above steps...

Regards

Ravi

Former Member
0 Kudos

If you setup transport routes in STMS, the default system will be the next system in the route.