on 10-07-2008 1:20 PM
hi
all
what is the use of ATP in PM order control
in capacity why we choose SAPSFCG013=3.0d
this is in spro-maint.ser order basic setting- avalability check material,prt
thanks
ATP is Available-to-Promise
the material check is there to ensure that you sufficient material required for the order in stock
in capacity the profie is defaulted - you can choose any of the options based on your requirements - see sap help on capacity planning to see the relevance of each profiles