on 10-07-2008 10:29 AM
Hi all
When i create Reservation for Maintenance order in PM system does not chack any budget.
is it any way that sys check the budget against the Reservation for Order.
Thanks
Shahid
Hi,
Reservation in PM is not defined as a commitment, and therefore still cant be record in FM.
The moment you will create a purchase requisition or purchase order, the FM will record the commitment, and budget will be reduce.
Hope I helped
Harel Cohen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Do you mean budget in FM? Did you configure the integration in Maintain Field Status for Assigning FM Account Assignments?
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.