hello friends,

when i do operational confirmation co11n as soon as i give order number, operation number in actual data field i want the planned times to display automatically. only if my actual times are different i shall change it. i know there is small setting in conf. parameters. can anyone guide me on this. thanks

sanju

replied

Hi,

For this: the T.Code: OPK0

Select the Standard Profile and in the Second Tab page " Defaults"

In the Default Values:

Selct for Quants and Services : Immediate Proposal.

With this system will propose the Times and Quantity during confirmation..

Regards,

Siva