Dear All SAP Gurus,
I have created PR release strategy but it is not working at header level.I have checked all the setting but coulnot getting problem why release is not coming to PR at header level.
Then i changed settings and made changes in the check boxes.I deselect the overall pr release checkbox at document type and release class screen.Then found that PR is getting release at item level.
My question is that why it is not working at header level when i select that both checkboxes at document type and release class type screen.
Please suggest me solution
Thanks and Regards
Mahesh
reolved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahesh,
Are you using same Release group for Overall and Item level release, or you have created another group for that, see if at all you are working in testing server you can try doing this.
Create New release group do all assignments and then try.
thanks & regards,
Prashant Rathore.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to SPRO > MM > Purchasing > Purchase Requisition > Define Document Types > Here for the PR Document Type, activate indicator "OverReqRel"
And also in SPRO > MM > Purchasing > Purchase Requisition > Release Procedure > Procedure with Classification > Set Up Procedure with Classification > Release Groups > Here also for the Release Group, activate indicator "OverReqRel"
Then check, it will start working.
Even if it is not working then delete the Release Group and all other settings and redo the same.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.