Availability date in batch management

Former Member
0 Kudos

How "Availability date" come from?

What is the relationship of "Date of creation" and "Availability date" ?

Edited by: Sasy on Oct 7, 2008 8:33 AM

Accepted Solutions (1)

Accepted Solutions (1)

former_member581212
Active Contributor
0 Kudos

Availability DAte = PO processing time + Gr processing time + Delivery time for the GR...

By adding above three parameters the system gives the Availability date...

GR processing time and Planned del. date is entered in MMR...

And PO processing date is entered in SPRO

Hope it helps...

regards

Priyanka.P