Helo folks
I have a requirement, i need to create a release strategy for PO at item level (release at item level). I know its is not possible but i got this requirement.
Plz guide me
thanq
V A M S I
Hi Why is this requirement is there any specific reason?
If you want to do it any way (If you want any field to be picked from item level to trigger the rel strategy). Then take the copy of that field and add it to Header data of PO (You can use screen or Field Exits here Check with ABAPer). and again define your release strategy as usual use the newly added field.
But this scenario is not required usualy as we have released PR at item level already so try to convince your requestor that it is not required to do this.
Thanks
Anand K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vamsi
Is there any specific example of the requirement. Generally it is not advisable to have a PO released at item level.
Thanks
Prashanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
P.O release at item level is not possible in Std SAP.
But you can do the Purchase requisition release at ITEM level
set Release procedure without classification for P.R.
Once P.R is released at item level you can create P.O and P.O can be released at Header Level
G.Ganesh Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Dont think item level release can be done for PO.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.