Regarding Negative Value

Hi all,

My end user uses russian reoprt (t.code:J3RFLVMOBVED) standard report for looking subcontractor stock during end of the month, in that some material price is different and in neagative for particular batch alone.

for example

Mat.no - 101003502

Org. price - 138.85

Price in report - 3,211.71-

Stock on End - 9,065

Cost Stock - 29,114,185.70-

Batch - 000071041

if the same is seen in MBLB it shows correct and no negative value.

mat.no - 101003502

price - 138.85

Stock - 9,065

Cost - 1,261,885.92

Batch - 0000071041

i've checked for negative stock allowed, negative MAP n STD price but found nothing wrong.

yet i'm getting negative value.

Kindly help me in this.