Commitment not getting updated while PR

Hello All,

I am facing a pecular problem.

1.) I have created an investment order

2.) The commitment management is active in controlling area and order type.

3.) I have assigned a budget to Invst.postion/order and avalilabity control is activated for order.

4.) I have tested the order for FI document, the system's show's the error"budget exceeded"

5.) I have entered the PR of it but the commitment is not getting updated.

6.) I have view the report S_ALR_87012806, Investment program structured report, in which the commitment for PR is not captured.

My requirement is to capture the commitments for CO objects.

Please help,

regards,

Anand