on 10-07-2008 5:35 AM
Hi Gurus,
I am for the first time getting involved in Data migration project in SD .
My question is what are the things that i need to Plan for Migration activities
1. Do i require technical team ?
2. how do we upload open sales orders, customer master data ?
please provide information
Hello,
If you are only uploading less number of data that too master data, you may do it with LSMW, doesn't require ABAP help. If you have large volume of data then you need to use BDC which needs ABAP coding.
In most of the companies, there will be programs to upload data. For Sales document upload, normally BDC will be used.
For master datas, QTP, LSMW can be used.
Prase
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Data migration can be done as mentioned by Prasanth either through LSMW, or through BDC.
Just to add a little more into it, that in case of BDC you might require ABAPer to write a program or i say customized program which will cater to your needs during data migration, like what sort of data are you looking at, and how it will be transfered from one server to another server.
Regards,
Abhijeet
Dear Yuvaraj,
1. Do i require technical team ?
-->Yes you require Technical team also to develop the up load program like BDC
2. how do we upload open sales orders, customer master data ?
-->You can upload Open sales orders through BDC
-->You can upload customer master through LSMW
I hope this will help you,
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.