on 10-07-2008 4:56 AM
Hello,
My Client earlier posted some transactions with old wbs element and later he renamed the WBS element.
When we checking the values with changed WBS element it's not giving the old WBS element values.
Is there any financial report gives the old wbs values into new wbs values.
As per my knowledge it will not update the old wbs values into new wbs values in financial reports.
If any body knows please provide the details.
Thanks in advance.
Regards,
satya
Dear satya,
if u have changed only description of wbs
then financial reports will show all values (old +new values).
it is already tested by me as i had changed the wbs description
in which some cost already posted.
after chenging description i had increase its budget and made one PO and its Service entry sheet.
when i m seeing in reoprt S_ALR_87013558 Budget/Actual/Commitment/Rem
it is showing all values.
so make sure r u seeing correct wbs.
Regards
Vivek tripathi
Edited by: vivek tripathi on Oct 7, 2008 7:06 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.