on 10-06-2008 3:22 PM
Hello,
I am using ESS for time recording within a cProject scenario.
When I want to record time and click on refresh appears an error message saying that I have to "Enter relevant working time attributes" and the work cent disappears.
In the configuration of the time record profile there is no field defined as a "must" field and I have no glue which field there has to be filled because the error message is really general.
Has someone an idea what I could do? I am using ESS 600 SP 13 Patch 6.
Thx, Vanessa
Hello,
the question is solved. The field receiver cost center was missing.
Thx, Vanessa