CKMPRPN

We don have material ledger active. We are thinking of ways to update ROH costs at the end of every month. For MR21 we need to delete the costing through CKR1 which we don't want to do. I can use future price fields in Costing 2 view but i want to know if we can use CKMPRPN.

i am not able to understand how this works? All I want is i should be able to update costs for next month so that the costing will pick these costs during the run?

Former Member
Not what you were looking for? View more on this topic or Ask a question