Enter "Delivery Completed"

whats is the procedure to enter "delivery completed"

Thanks in advance

Ganga

replied

Hi,

You can activate "Delivery Completed" indicator in PO (ME22N), for the PO line item in "Delivery" tab if further GR is not expected.

If you don't want to allow user to ammend PO the at the time of GR in MIGO, under "Purchase Order" tab, you can select value as "Set" for Delivery Completed field if further GR is not expected, it will mark "Delivery Completed" indicator in PO automatically for that line item in "Delivery" tab.