Hi All,

Could you please tell me how to trigger a process chain using background job ?

Thanks,.

Former Member
replied

Write a program to achive this based on your condition raise the event using function module.

BP_EVENT_RAISE

In the the process chain in the start process in scheduling options-----> use AFTER EVENT.

To create a event you can in SM62.