cancel
Showing results for 
Search instead for 
Did you mean: 

activity assinment

Former Member
0 Kudos

No structure could be determined for internal activity no xxxx for cost center xxxx

while production order relesethis error message came

can anybody guide me

Edited by: sap pp on Oct 6, 2008 12:26 PM

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

What is message no?

check if all the activities are assigned activity units & rates.in KP26?

Regards,

R.Brahmankar

Edited by: R Brahmankar on Oct 6, 2008 4:21 PM

Former Member
0 Kudos

messge no NA CK 694

kp26 is ok

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

First check this activity is palnned in KP26 / KP06 for the period concerned

One more checking is in OKTZ, is the cost element is assign to a cost component structure?

Regards,

R.Brahmankar

Answers (1)

Answers (1)

former_member196398
Active Contributor
0 Kudos

Hi,

Please check in transaction "KP26" for the Cost Center and Activity Combination for the current period whether price is maintained, if it is not maintained please maintain it.

Regards,

Prasobh