project definition system status change details
Dear PS experts,
Request, kindly let me know which report is available to show the system status change from
crtd to rel
rel to teco
teco to clsd
we would like to analyse which date or period the system status changed thru edit-status
from crtd to rel
rel to teco
teco to clsd
we don't use any user status.
i have checked cn60 & all reports from cn41 to cn47, but i don't get any report states about the change details of system status.
pl help
srihari
Former Member replied
hi srihari,
Try to create querry using querry reporting ...
use sq01,sq02,sq03 tcodes
1.create user in sq03,
2.create infoset in sq02, and generate that and back again in sq03 assign user group to infoset .
3.In sq01 create a querry using the infoset developed in sq02.
4.In infoset u select the table as suggested by others and the fields.
Ther is not development involved in this ....
regards