HI PP Experts,

Can any body tell me why do we create PIR.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

PIR means Planned Independent requirement. It is nothing but a demand or requirement. It is your own plan based on future customer req .

After MRP run this requirement will convert to planned order and this planned order will convert to production order to start a production.

Regards,

Dharma

Former Member
0 Kudos

Good answer,satiesfied.