Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Error when converting planned order to production order

Dear Gurus,

I am working on ECC 6.0 for MTO scenario for a configurable material.

When I run MD50 and then try to convert planned order in production order it gives me following error:

error message CO684: 'You cannot make an assignment to make-to-order stock'.

I am using requirement class 46 and strategy is 25. In the requirement class, the account assignment is M and valuation is also maintained as M.

Also for the production order type, the settlement profile assigned has settlement rule optional for sales order, profitability segment, cost center....

Also in the controlling area, Sales Order is activated.

Kindly advice and thanks in advance.

Regards,

Niraj

Former Member
Not what you were looking for? View more on this topic or Ask a question