Dear Gurus,
I am working on ECC 6.0 for MTO scenario for a configurable material.
When I run MD50 and then try to convert planned order in production order it gives me following error:
error message CO684: 'You cannot make an assignment to make-to-order stock'.
I am using requirement class 46 and strategy is 25. In the requirement class, the account assignment is M and valuation is also maintained as M.
Also for the production order type, the settlement profile assigned has settlement rule optional for sales order, profitability segment, cost center....
Also in the controlling area, Sales Order is activated.
Kindly advice and thanks in advance.
Regards,
Niraj
Dear,
Please check your planned order under "Assignment tab" whether the sales order is visible?
Find out what is the settlement profile assigned in your Order Type; TC: OPJH
and in customizing see for that settlement profile whether for Sales Order : settlement is allowed or not. If not change accordingly. And check again.
Please refer to SAP Note 861670 and 432109 or 311651
Also refer this thread,
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Can you please check in the planned order whether you find the Sales Order Item details in the account assignment tab? If not please delete this planned order and then try running MD50.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.