Hello Guru,
i would like to know why does the production finish date differ when we do manual and conversion of planned order into a production order?
Thanks
Ryan,
When a planned order is created it just uses the Inhouse production time defined to derive the dates, whereas incase of production orders, it would try to schedule the operation and based on that the scheduled dates are derived. The other possibility is the different scheduling types are used for Planned order and Production order. Check transaction OPU5 and OPU3
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It depends on scheduling type & Reduction strategy what you maintained in Define parameters for production order - tcode OPU3.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.