For newly created plant I released the production order, but costing error came

Message that no price could be determined for material XXXX/plant xxxx

Initially I have not marked and released the cost by ck40n and ck24

Wat could be the reason ,

Former Member
Former Member replied

Hi,

Go to CO03, production order display and Control Data Tab. According to the " planned cost calc field, cost being planned by the system. So, while saving or releasing the production order, you must have released the Cost estimate for the finished material. If not, you will be getting this error.