ho to map the warehouse plants and factories.

i will run mrp in warehouse plants.plz help me

Thanks

Rakesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Dhrama,

Thanks for giving the valubale information.I have maintained the strategy in warehouse plants not in factories. I will run mrp in warehouse plants. how the planned orders transfered to factories.

Thanks

rakesh

Former Member
0 Kudos

Hi,

Assign spl.procurement key 70 or 80 in warehouse and run MRP.

In SPRO > MRP> Master data > Spl.procurement type. Enter Issue plant.

When MRp run system will create planning proposal in another plant.

Regards,

Dharma

Former Member
0 Kudos

Hi,

In SAP you can consider factory is also a plant.

Consider Warehouse as a main palnt, factory as an another plant.

By using spl.procurement key by running MRP in warehouse, you can plan for factory. (MRP2 view)

Ex. Spl.procurement key 40 - Stock transfer from plant to plant

Spl. pro key 70 - Withdrawl from alternate plant

Spl. pro key 80 - Production in alternate plant

Regards,

Dharm