CK40N

Hi there,

We have done a upgrade form 4.6 to ECC 6. The usual behavior of CK40N is it costs all the FGs and SFGs which have no problem and it gives a error log for all the material which has some problem in their raw material/routing or on some other parameter.

But in our case it start costing materials and as soon as it find one material which has some problem, it stops costing and gives error for that particular product. This is consuming lot of time as it keeps giving error and stops costing till all material in the selection are become problem free.

Am I missing some setting?

Please respond.

Thanks and Regards

Deepshikha