Dear All,

I would like to know is it possible to make the field PLPOD-INFNR as a required input field for the control key PP02 for a particular plant?

I checked in OP5B & OP5D, but not quite sure how to link the 2, as plant is at header level & info-rec no. is at operation level.

Hope my request is clear.

Vivek

replied

Dear Vivek,

It is possible through using a screen variant or transaction variant.

Regards,

Ram