Hi,

My client handles assembling of electronic products. product passes through different set of operations where in it proceeds to the next operation only when the prior operation is approved in terms of quality.

We are trying to go with repetitve mfg but we are unable to understand in-process inspection operation wise. Pls advise is this feasible or we only need to go with discrete mfg with production orders.

Regards,

Sravan Kumar V

Edited by: SRAVAN KUMAR on Oct 6, 2008 6:45 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

1. Setting up inprocess inspection

for inprocess REM you have to maintained inspection type 13 in material master. and select task list. for that you have to maintained inspection point in your rate routing for ex for partial lot quantity based.

2. GR Inspection from production

then you go for result recording for inspection point and do the reporting point backflushed through result recording of every inspection point.

3. At what stage the QM lot is generated .

for that you have to create inspection lot in t code MFPR for your production version and for that inspection lot you have do above work.

Please refer this link also,

http://help.sap.com/saphelp_46c/helpdata/en/8a/a5aadd4adc11d189740000e8322d00/frameset.htm

Regards,