Dear Friends

How do we configure Version No. T.code : OMP2, how do we configure a new version no and make it inactive (version should be inactive while creating Planned independent requirements.

Thanks in Advance

Jade.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can define the version through the path:SPRO - Production - Production Planning - Demand management - Planned Independent requirements - Define version numbers.

Making the version active or inactive, can be controlled while loading the demand in MD61. If you need the version to be active, you need to check the active box. For inactive version, you should not check the active box.

Regards,

V. Suresh

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

OMP2 is only use to create the version number. and requirement type: OMP1 We can not create the inactive or active version here you need to define it in MC88, MC94 or MD61.

Regards,

R.Brahmankar