Hello

How is the Assembly Planning Indicator in the Demand tab of the Location Product Master set ?

Should this be set manually in APO or through R3 ??If manually, whats the best practise to maintain this indicator ?

Thanks

Former Member
Former Member replied

Please maintain below setting for Strategy 70 :

Strategy group 70 on the MRP screen.

Set the indicator for assembly planning, the Mixed MRP indicator, to 1 on the MRP screen.

Consumption parameters (Consumption mode, Bwd consumption, Fwd consumption on the MRP screen) to allow for consumption of planned independent requirements.

If you are using this strategy in a make-to-stock environment, you also must set the Individual/coll. indicator to 2 on the MRP screen.

Also again do the Initial transfer by RIMODINI