on 10-05-2008 7:55 AM
Hello
How is the Assembly Planning Indicator in the Demand tab of the Location Product Master set ?
Should this be set manually in APO or through R3 ??If manually, whats the best practise to maintain this indicator ?
Thanks
Subassembly planning strategy 70 in R/3 gets transferred to APO as requirement strategy 20 with Assembly Planning indicator in the Demand tab of the Location Product Master .
Also wants to set is manually you can do it by MASSD tcode or LSMW.
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please maintain below setting for Strategy 70 :
Strategy group 70 on the MRP screen.
Set the indicator for assembly planning, the Mixed MRP indicator, to 1 on the MRP screen.
Consumption parameters (Consumption mode, Bwd consumption, Fwd consumption on the MRP screen) to allow for consumption of planned independent requirements.
If you are using this strategy in a make-to-stock environment, you also must set the Individual/coll. indicator to 2 on the MRP screen.
Also again do the Initial transfer by RIMODINI