How to use Different Calendars in one DP Planning Area

Hi Experts,

I would like to know that whether it is possible to use different calendars in single planning area ? Will explain the scenario in details as under

We have 3 plants having separate calendars (different weekly offs). Now using single planning area in DP, I have to plan the demand for all the 3 plants in weekly buckets.So I need to refer to 3 different calendars in single planning area. Is this possible in DP ? As far as I know, we can attach only one fiscal year variant to the planning area through storage bucket profile. Also in this case, the system do not refer to public holiday calendar there by assuming all day working except the weekly off.

Thanks in advance

Regards

Sandeep