Pick/Pull list

Former Member
0 Kudos

Hi PP Experts,

Can anybody explain me what is use of Pick list and Pull list.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

PIck List:

Pick List is a document by which you carry out Goods Issue for the required materials from Storage location by Production order wise , material wise etc.By pick list you generate reservation for the particular materials and then issue them against that reservation for shop floor manufacturing.

You can print the list, assemble the requested materials from the storage location accordingly, and post the goods issue via the pick list.

Pull List

Purpose

The pull list controls the in-house flow of material for supplying production with materials. The system assumes that the components required for production have already been produced in-house or procured externally and are now available to be transferred from their current storage location or bin to the production storage location.

The pull list checks the stock situation at the production storage location and calculates the quantities of missing parts. Replenishment elements can be created for these missing parts. Components can be staged via direct stock transfer or using stock transfer reservations. Replenishment can also be triggered by setting a kanban to u2018emptyu2019 or creating transfer requirements in Warehouse Management.

Integration

The pull list is an integral part of repetitive manufacturing and shop floor control.

The basis of replenishment planning is MRP - the component requirements are calculated in the MRP run. The system takes requirements from run schedule quantities, production order reservations and manual reservations into account.

Depending on the environment, replenishment can consist either of direct stock transfer, stock transfer reservations, kanbans or transfer requirements, which are then processed in the appropriate module.

Features

You can access the pull list by material to be produced (that is, by assembly), by component, production line or MRP controller, amongst others.

The pull list calculates the missing parts by checking which requirements fall within a certain period of time, which stocks are available in the production storage location, and which replenishment quantities have already been initiated via the pull list.

You can also use the pull list to create replenishment elements for the missing parts. The system first creates a replenishment proposal for the missing parts. The system can post this proposal as a replenishment element (stock transfer reservation, kanban or WM), or carry out a direct stock transfer.

Constraints

It is not the primary task of the pull list to determine the location of the required components. The only exception is in the direct stock transfer procedure where you have to enter a replenishment storage location or the system has to determine a replenishment storage location via stock determination.

The pull list is primarily responsible for planning material staging (calculating missing parts and initiating replenishment) by creating a work list in the form of replenishment elements. The actual staging is carried out by a warehouse clerk, for example, and is supported by transactions which are carried out subsequently, based on the replenishment elements.

Hope this helps.

Regards,

Tejas