What is meant by MRP Controller and What is the T-code for Creation of MRP Controller? Explain with examples.
Hi,
Definition: MRP controller
Material Requirements Planning (PP-MRP)
The person responsible for a group of materials in MRP in a plant or company.
Material that takes part in material requirements planning must be assigned to an MRP controller.
You can define MRP Controller by following way:
SPRO--> Production>Material Requirement Planning>Master Data-->Define MRP Controllers
Pls find some more details about maintaining MRP Controller:
Define MRP Controllers
In this step, you define a number that is assigned to the MRP controller.
The MRP controller is a person or a group of persons responsible for monitoring material availability. You can use the number entered here, for example, to select the planning results per MRP conroller.
Every material that is relevant to the planning run must be assigned an MRP controller number in the material master record.
You can also determine a special person for backorder processing who receives a mail if a goods receipt was posted for a missing part. You must enter the mail name of this person in the field entitled, recipient name.
In addition, you can define a person or a group of persons, who are to informed if you send a mail from the MRP list or stock/requirements list to the MRP controller for the material displayed.
Actions
Enter the MRP controller and maintain the mail recipient, if necessary.
HOpe this helps.
Regards,
Tejas
Edited by: Tejas Pujara on Oct 4, 2008 6:58 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To create the MRP Controller there is no t-code.
Path is like this -
IMG --> Production --> MRP --> Master Data --> Define MRP Controller.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The MRP controller is a person or a group of persons responsible for
monitoring material availability.
Without MRP controller u can't take the MRP run.
On the basis of MRP controller u can execute number of reports like COOIS, COOISPI, MD04, etc.
Regards
Ashish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.