Project wise profitability analysis

Hi

I have to create MIS for project wise profitability analysis . In sales order we used additional tab as project and we assigned projects to each and every sales order

Now they want one Report "Project wise profitability analysis" . So i have do that through Infoset (Lis)

Please tell me what are the charecteristics & what are the keyfields to select to get the cost

(i want material number - Planned cost - Actual cost - variance)

Rgds

pradeep

Former Member
Former Member replied

Hi,

This is standard report to get acutal cost and planned cost and variance.

S_ALR_87013532 - Plan/Actual/Variance

S_ALR_87013566 - Actual Contribution Margin

S_ALR_87013568 - Project Results

Regards,

Chandra