on 10-03-2008 2:44 PM
hi all,
i 've created 2 strategies (z1 n z2) for PO rleased. For Z1 - PGrp1, plant 1100, and value >1000 n <5000 are the values for classification.
But when i'm creating PO the following are observations.
case-1: for Pgrp1, p-1100 and value 10000 the defaulted strategy is Z1 - observation is as per the classification system should n't pick up strategy for PO with value >5000.
case-2: for Pgrp1, p-1200 and value 4000 the defaulted strategy is Z1 - observation is as per the classification system should n't pick up strategy for for plant 1200 as it is not defined in the classification.
my question is if only the header field is the criterion for picking rel strategy, how can i classify my rel strategy according to value.
regds
kirla/IBM
i think you have not defiend the classification properly
please tell us
the calssification you have used with value.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.