on 10-03-2008 2:32 PM
Hi gurus,
Pls tell me what is the TCODE for Process order creation against Sales order
Eg. CO07 is for production order from sales orde
I too have yet to find a "true" transaction, although you can use COR1, click on the "select reference object" which is at the side of the Copy From Process order ( I know it's not the best place for it to be!) then you can enter the sales order and the line item.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Typically, in MTO scenario after the sales order is created you run MRP which will create planned order and then you convert that into production order using MD04.
Or if you have SD settings correctly directly from the release of Sales Order it will create planned order or production order.
please check and revert back.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.