What happens while trying to run MRP without activating Requirement planni

Former Member
0 Kudos

Dear Frndz,

Plz explain me the consequences, if I try to run the MRP without activating the requirement planning in customizing.

Regards,

Srinivasan Muthu.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If MRP is not activated, No planning file entries exist for the materials.

MRP generates requirements only for materials with "Planning relevance" in planning file entries.

Since the system will not find any planning relevant material, no MRP element (plnd order /pur reqsn) will be generated even if the material has requiremnts.

regards,

Ashok

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

You will get error message" Requirement planning is not active for plant-------"

Regards,

Rajaram.k

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

System will not get any planned order even if requirement is there.

first u need to activate MRP for the plant in the tcode OMDU

then u need to Carry Out Overall Maintenance of Plant Parameters in the tcode OMI8

then u need to carry out Carry Out Overall Maintenance of MRP Groups in OPPZ .

then u need to have activate MRP view in material master for that plant.

enter the mrp type andd enter the details for the selected MRP type.

u can run mrp using Total Planning (MD01)

or MD02 -etc

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

Without activating material requirement planning, entry will not made in the planning file while create material or make changes in MRP related elements like date,qty ,lot size ,MRP type.

Regards,

Dharma