Dear Frndz,
Plz explain me the consequences, if I try to run the MRP without activating the requirement planning in customizing.
Regards,
Srinivasan Muthu.
Hi,
If MRP is not activated, No planning file entries exist for the materials.
MRP generates requirements only for materials with "Planning relevance" in planning file entries.
Since the system will not find any planning relevant material, no MRP element (plnd order /pur reqsn) will be generated even if the material has requiremnts.
regards,
Ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You will get error message" Requirement planning is not active for plant-------"
Regards,
Rajaram.k
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
System will not get any planned order even if requirement is there.
first u need to activate MRP for the plant in the tcode OMDU
then u need to Carry Out Overall Maintenance of Plant Parameters in the tcode OMI8
then u need to carry out Carry Out Overall Maintenance of MRP Groups in OPPZ .
then u need to have activate MRP view in material master for that plant.
enter the mrp type andd enter the details for the selected MRP type.
u can run mrp using Total Planning (MD01)
or MD02 -etc
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Without activating material requirement planning, entry will not made in the planning file while create material or make changes in MRP related elements like date,qty ,lot size ,MRP type.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.