Former Member
0 Kudos

Hi,

I make a PO where Release strategy is 6 (>50k), one of my approver rejects the PO. The buyer changes the PO quantity to the extent that value becomes lower than 50k, but my release is not getting changed. Its still 6.

But same qty change if i do from approvers ID ,release strategy gets changed to 3 (between 10k-50k)

Regards,

Satyendra

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Is the Buyer added to teh M_EINK_FRG Role?? You might want to discuss tihs with your security or you could execute PFCG and check it your self.