in CORT(process order confirmation) in operation 440

0 Kudos

in CORT(process order confirmation) in operation 440. the already confirm is not similar to the already confirm of operation 530 cofirmation production.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Check the control key for both the operations. Also check if the users have done CORK (order level confirmation) intead of COR6 (operation-phase level)....In COR6 if you do not maintain the activity yield value (at the bottom section of screen) then in CORT it might be displayed as blank...

I had faced the same issue...and the user had done incorrect confirmation hence CORT was not being displayed the same.

Please check and revert back.

0 Kudos

hi

kindly elaborate your answer. the control key for operation 440 is PI29 while the control key for 530 is PI34

Former Member
0 Kudos

Hi

Could you please ellaborate your question?