on 10-03-2008 11:11 AM
in CORT(process order confirmation) in operation 440. the already confirm is not similar to the already confirm of operation 530 cofirmation production.
Check the control key for both the operations. Also check if the users have done CORK (order level confirmation) intead of COR6 (operation-phase level)....In COR6 if you do not maintain the activity yield value (at the bottom section of screen) then in CORT it might be displayed as blank...
I had faced the same issue...and the user had done incorrect confirmation hence CORT was not being displayed the same.
Please check and revert back.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Could you please ellaborate your question?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.