Hello,
It is allowed in the sales order to change the profit center. I want to copy the entered profit center from my sales order to the profit center of my linked production order which has been created automatically.
I tried already some user-exits (enhancements PPCO000?) but it doesn't work. Who can help me solving this problem?
Many thanks for helping,
Bart
Dear,
Maintain the Profit Centre in Costing 1 View of Material Master.
Then it will be defaulted into the Production Order.
Profit center can be entered at the item level in the sales order T.Code: VA01, in the Account Assignment Section.
If Profit Centre is maintained in Material Master Data, in Sales: General / Plant data, then the same will default in sales order.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.