Budget consumption in a project

Hi All,

I want to have budget controll for already existing projects running for the last 1-2 years.

All required configuration needed for budget control for projects are done well & fine.

Now when I alot budget to these projects , the budget first get consumed for the activities which have been performed under this project in the previous periods.

Our requirement is like the budget controll should be active from the day we have alloted the budget to the project and should not take into consideration the consumption in the previous period.

Is it possible to achieve this requirement.

Former Member