I have to develop a report on PREQ to find out how long it took to get it released.
For this report the time will be calculated from the date when the PREQ was created and when it got finally released.
My issue is the EBAN table does not have PREQ create date, it gives the change dates only.
Pl help in which table the date of creation is stored in case of PREQ.
Hi,
This you will not find in EBAN ,For this check table CDHDR. Input OBJECTCLAS = 'BANF'
and input PR no in Object ID
and for TCODE= 'ME51N' and execute.
You will get the date and time of PR creation.
Dhruba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Purchase Requisition Request Date / Created Date both are Same. If you are Looking for ERDAT then it Will Change whenever Purchase Requisition Changes.
So, Check the BADAT Requisition (Request ) Date & FRGDT Released date and your Problem will Solve.
FRGDT - BADAT
Revert back in case doubt...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.