cancel
Showing results for 
Search instead for 
Did you mean: 

SAP PP-Planning at Assembly level(70)u201D & u201C Planning at Assembly level witho

Former Member
0 Kudos

Hello SAP-Guruu2019s

Pls explain the Strategy u201C Planning at Assembly level(70)u201D & u201C Planning at Assembly level without final Assembly (74)u201D and pls give any examples if possible.

Thanks in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Planning at Assembly Level (70)

Purpose

This planning strategy is particularly useful for manufacturers of products with variants if a more

reliable forecast can be produced for certain assemblies than for the multitude of product

variants.

Prerequisites

You must maintain the master data of the assembly as follows:

Strategy group 70 on the MRP screen.

Set the indicator for assembly planning, the Mixed MRP indicator, to 1 on the MRP

screen.

Consumption parameters (Consumption mode, Bwd consumption, Fwd consumption on

the MRP screen) to allow for consumption of planned independent requirements.

If you are using this strategy in a make-to-stock environment, you also must set the

Individual/coll. indicator to 2 on the MRP screen.

Reduction

Consumption

This strategy is very similar to Planning with Final Assembly (40) However, planned

independent requirements are consumed by production order requirements (or schedule lines in

repetitive manufacturing) and not to requirements of sales orders.

1. Stock for the assembly usually exists.

2. Planned independent requirements are entered at assembly level. Procurement (planned

by means of the planned independent requirements) is therefore triggered before the

production order stage (or schedule line in repetitive manufacturing).

3. The planned orders for the assembly/components are convertible.

4. Procurement smoothing according to order demand is possible. In this strategy,

however, the ability to react flexibly to customer requirements is more important.

5. An accurate availability check is performed according to ATP logic during production

order processing.

6. Requirements from production orders (or schedule lines) are passed on to production

and can lead to changes to procurement after the sales order stage, if the order

quantities exceed the planned independent requirement quantities. However the order

quantities cannot be confirmed if there is insufficient coverage of components. The

system automatically adjusts the master plan. For more information see Coping with

Insufficient Coverage of Components .

7. The planned independent requirements are consumed during the production stage. This

means that you can compare the planned independent requirements situation with the

actual order requirements.

Unconsumed planned independent requirement quantities increase the warehouse stock of the

component, and cause procurement to be decreased or not to take place at all in the next period.

This procedure is called "netting."

Sample Scenario: Strategy 70

Process Flow

This example is based on a production plan in which 100 pieces are planned for <reqdat1>,

<reqdat2>, and <reqdat1>.

Stage 1: Demand Management

1.In this scenario, planned independent requirements are created as follows for the

production plan.

Period indicator Reqmts date Planned qty Value

T (= day) <reqdat1> 100 10,000.00

T (= day) <reqdat2> 100 10,000.00

T (= day) <reqdat3> 100 10,000.00

The system will find requirements type VSFB because the strategy group has been set

to 70.

2. The requirements are passed on to MRP. The stock/requirements list (Logistics

Production MRP Evaluations Stock/reqmts list) displays the following

information:

Date MRP element MRP element data Received/

required

quantity

Available quantity

<today> Stock 0

<reqdat1> IndReq VSFB 100 - 100 -

<reqdat2> IndReq VSFB 100 - 200 -

<reqdat3> IndReq VSFB 100 - 300 -

Stage 2: Procurement Before Use in Production

1. A procurement requisition is created in the MRP run (Logistics Production MRP

Total planning). The stock/requirements list displays the following information:

Date MRP element MRP element data Received/

required

quantity

Available quantity

<today> Stock 0

<reqdat1> PlOrd. 123/STCK 100 100

<reqdat1> IndReq VSFB 100 - 0

<reqdat2> PlOrd. 124/STCK 100 100

<reqdat2> IndReq VSFB 100 - 0

<reqdat3> PlOrd. 125/STCK 100 100

<reqdat3> IndReq VSFB 100 - 0

This procurement requisition is the starting point for production or external procurement.

You have a variety of options for handling the procurement process in the R/3 System.

One possibility would be to convert the planned order into a production order, release of

the production order and a goods receipt of the yield quantity. It is also possible,

however, to use returns or other goods movements for make-to-stock production.

2. After goods receipt for the order, the stock/requirements list displays the following

information:

Date MRP element MRP element data Received/

required

quantity

Available quantity

<today> Stock 200

<reqdat1> IndReq VSFB 100 - 100

<reqdat2> IndReq VSFB 100 - 0

<reqdat3> PlOrd. 125/SDeb 100 100

<reqdat3> IndReq VSFB 100 - 0

Stage 3: Production Order and Allocation

A production order that uses the planned component is created (Logistics Production

Production control Order Create).

An availability check is performed in the order (Component Availability Check availability).

In this example, it is assumed that production is 50 pieces of the material and the

material has an in-house production time of zero.

A popup appears containing the following information:

Requirements date <today>

Requirements quantity 50

Availability check (checking group) 02

ATP quantity 200

Confirmation date <today>

Confirmation quantity 50

This availability check is always performed according to ATP logic. See Availability Check [Page

157].

The production order quantity, which is not visible in the production order, is allocated to the

component quantity. You can, however, control the allocation in the stock/requirements list or in

the total requirements list. The total requirements list displays the following information:

Requirements type Date Allocated quantity Total quantity

VSFB 300

<reqdat1> 100

RESE <reqdat1> 50

<today> 50

<reqdat2> 100

<reqdat3> 100

After creation of the production order, the stock/requirements list displays the following

information:

Date MRP element MRP element data Received/

required

quantity

Available quantity

<today> Stock 200

<today> OrdRes SZ-10 50 - 150

<reqdat1> IndReq VSFB 50 - 100

<reqdat2> IndReq VSFB 100 - 0

<reqdat3> PlOrd. 125/STCK 100 100

<reqdat3> IndReq VSFB 100 - 0

Any parent material that consists of this component is automatically allocated to this plan. In

practice, there are several header materials (like SZ-10 in this example) that allocate this

material.

Stage 4: Procurement After Production

This does not apply to this strategy.

Stage 5: Goods Issue for Production Order

After goods issue for the production order (Logistics Materials management Inventory

management Goods movement Goods issue), the stock/requirements list displays the

following information:

Date MRP element MRP element data Received/

required

quantity

Available quantity

<today> Stock 150

< reqdat1> IndReq VSFB 50 - 100

<reqdat2> IndReq VSFB 100 - 0

<reqdat3> PlOrd. 125/STCK 100 100

<reqdat3> IndReq VSFB 100 - 0

Hope this helps.

Regards,

Tejas