plan order poblem while creation

Dear All

I have created Planned Independent Requriement in MD61.requirment type is VSF planning time in month

Then I run MRP in MD02, but it only showing ind requirment but not plan order against that.

Regards

Shrinivasan

Former Member
replied

Dear,

Mrp type X0 means the material is relevant for APO and its planning is to be done in APO and not R/3

So you will not get planned order in R/3.

Preferred MRP type is PD & VB

Please come back if any query.

Regards,

R.Brahmankar