on 10-03-2008 6:21 AM
Dear Friends,
I want to run Standard Cost estimate without BOM. I am having only activities. For example... I am manufacturing OXYGEN by taking the natural air. Natural air I am not maintainingin stock... it is not a material for me. But I am having different activities for manufacting OXYGEN.. I want to run standard cost with only routing... How can I do it? I tried.. but system is giving a error saying that "No BOM elements with relevancy to costing"
Thanks in Advance.
Regards.
One option is to create the natural air as a pipeline material, with an extremely low price, so that it is effectively nil in your calculations.
The other is to switch off the error message you are getting.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.