HELLO FRIENDS,
IS THERE ANY WAY TO SHORT CLOSE A SERVICE PO WITHOUT AMENDING THE PO VALUE AND QUANTITY, LIKE WE DO FOR A MATERIAL PO.
Go to ML81N and Select Menu Entry sheet and Select Set Status as Final Entry
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For a Material assigned Purchase Order you can Set Delivery Complete Indicatory to Stop Further Processings / GR.
But, For a Service Purchase Order Service Entry sheet will be Done instead of GR which will create GR Material Document in Back ground.
So the Only way is to Set the Final Entry in the Last Service Entry sheet.
Go to ML81 /ML81N and in Menu Service Entry sheet - Set Status - Final Entry and Save such that no Furhter Entry sheets are allowed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.