WBS scheduling profile - what is it used for?

Former Member
0 Kudos

Hi,

I would like to understand what is WBS Scheduling and what is the config path to confugure WBS Scheduling profile.

Thanks!

Regards,

Vivian

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

scheduling profile is used to determing the scheduling type and method of how the system calculates dates for the WBS elements in the project.

you can configure scheduling profile in path: IMG > Project System > Dates > Date Planning in WBS > Define Parameters for WBS Scheduling

other settings can also be made in IMG > Project System > Dates > Scheduling

hope it helps..

Former Member
0 Kudos

Hi Ramesh,

Thanks for your reply. Just need help to visualize what 'scheduling' is for, can you let me know what is the transaction to 'schedule WBS' so that I can see how it looks like and how it works.

Thanks!

Regards,

Vivian

Former Member
0 Kudos

you can schedule projects in CJ20N and click on Project Planning Board and utilize the diff functions..

you can also use CJ21 - Change Basic Dates, CJ23 - Change Forecast dates, CJ25 - change actual dates, CJ29 - Project Scheduling..

see also this link:

http://help.sap.com/saphelp_erp60_sp/helpdata/en/c0/1885347860ea35e10000009b38f83b/frameset.htm

regards