missing parts if GR date is past requirement date

Former Member
0 Kudos

why am i getting a missing parts message if the GR date / delivery date of the material is past the requirement date of component in the order? couldn't it be possible to make these components available, for more flexibility in the system?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi!,

Please check your "availability check control" for the combination of your checking group (e.g. '02') and checking rule (e.g. 'PP') on trnx OPJJ.

There do the following settings:

1. Incl. Purchase orders: Select

2. Incl. purchase requisitions: Select

3. Incl. Planned orders: select' X'

Or

On OPJK, for your plant and order type combination and avlb check '2' set release material as '1' or '2''. This will help user to release the order even in case of material shortage.

I think this may solve your issue. Please revert back in case of any further issue.

Regards,

Uday

Edited by: Uday Parchure on Oct 3, 2008 7:30 AM

Former Member
0 Kudos

why do i need to select all three? if i check PR and PO, does it mean that PRs and POs are read as stock even if they are not in the plant yet?

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please check the OVZ2 no check active and MIRO.

Did you check the Transaction code OPJ2.

The "No Stock" indicator is checked?

Regards,

R.Brahmankar

Answers (1)

Answers (1)

Former Member
0 Kudos

HI

1.please check the stock available or not.

2.If available -when is the order created?when the stock came into storage location?

3.what is the exact error your facing?