why am i getting a missing parts message if the GR date / delivery date of the material is past the requirement date of component in the order? couldn't it be possible to make these components available, for more flexibility in the system?
Hi!,
Please check your "availability check control" for the combination of your checking group (e.g. '02') and checking rule (e.g. 'PP') on trnx OPJJ.
There do the following settings:
1. Incl. Purchase orders: Select
2. Incl. purchase requisitions: Select
3. Incl. Planned orders: select' X'
Or
On OPJK, for your plant and order type combination and avlb check '2' set release material as '1' or '2''. This will help user to release the order even in case of material shortage.
I think this may solve your issue. Please revert back in case of any further issue.
Regards,
Uday
Edited by: Uday Parchure on Oct 3, 2008 7:30 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
1.please check the stock available or not.
2.If available -when is the order created?when the stock came into storage location?
3.what is the exact error your facing?
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.