Settlement rule for Network activity

Former Member
0 Kudos

hi,

in my project, settlement rule of network activity is automatic to the superior WBS.. however i noticed that the default settlement rule is FUL.. is it possible to make setting such that the default settlement rule would still be to the superior WBS but it is PER (periodic settlement insted of full)

how to do this?

thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

see OSS note 317871

Summary

Symptom

When you create a network or a new network activity, the respective settlement rules can be generated automatically by default. In the standard system, default rule PS1 is currently supported for this. This default rule creates a settlement rule for the full settlement.

A default rule for the generation of a settlement rule for periodic settlement does currently not exist.

Additional key words

CN21, settlement rule

Cause and prerequisites

At present, the function is not supported in the standard system.

Solution

The attached program creates a corresponding new default rule PS2 which generates a periodic rule. In Customizing, you can assign this default rule to the affected network types afterwards.

It is planned to include this default rule in a future release in the standard system.

Source code corrections

Header Data

Release Status: Released for Customer

Released on: 18.06.2007 07:57:36

Priority: Recommendations/additional info

Category: Advance development

Primary Component: PS-COS-PER Automatic and Periodic Allocations

Secondary Components: PS-COS-PER-SE Settlement

Affected Releases

Software

Component Release From

Release To

Release And

subsequent

SAP_APPL 40 40B 40B

SAP_APPL 45 45B 45B

SAP_APPL 46 46B 46B

SAP_APPL 46C 46C 46C

SAP_APPL 470 470 470 X

SAP_APPL 500 500 500

SAP_APPL 600 600 600

Answers (0)