Folks
Through CA71, WBS BOM can be created by providing WBS element, Materal, plant, BOM usage. I had created a routing as well.
Does the standard CIF support transferring WBS BOM (Work Break down structure) to APO?
Through R3, there is a transaction, CURTO_CREATE_FOCUS, which manually transfers WBS BOM as PPDS PDS into APO.
R3 Path for CURTO_CREATE_FOCUS : Logistics ->Central Functions ->Supply Chain Planning Interface ->Core Interface Advanced Planning and Optimization ->Integration Model ->Change Transfer ->Production Data Structure (PDS) ->Transfer Order BOM/WBS BOM.
Now I am trying to know if thee is a possibility or feature that SAP offers to trasfer the WBS BOM, can upon its creation in R3 instead of manually trigeering the CURTO_CREATE_FOCUS program.
Would appreciate if anyone can let me know if this is possible and if so the process, config invloved.
Thanks
Edited by: p706063 on Oct 3, 2008 10:11 PM
I guess you have to check the possibility of CIF Enhancement
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To transfer it automatically , please create a variant for the program :CURTO_CIF_CREATE_FOCUS_RTO and do background scheduling with your CIF job.
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.