MRP Type V1 and Planning horizon

Hi Gurus,

I have made a change in customizing of MRP Type V1.

I have selected include ext. reqmts option as 1(External requirements in total horizon).

I have entered the planning horizon in OPPQ transaction as 100 days and given required delivery date after 2years. No MRP group assigned in material master.

When I create a sales order, it is creating a procurement proposal even though the Required delivery date is out of planning horizon period

Please tell me that other than OPPQ and OPPR where do we mention

the planning horizon. Why it is creating a procurement proposal out of planning horizon.

Please note that I have a habit of awarding points to every contribution.

Regards,

Jejesh

Former Member
replied

Dear,

Planning Horizon of 100 is not considered (does not take into effect) during the NETPL planning run. So please check your MRP processing key?

Also check the net change indicator is set for changes within the planning horizon.

System plan only materials have MRP relevant changes in planning file entry.

Planning horizon is maintained at plant level or MRP Group level in T Code OMDX

Regards,

R.Brahmankar