No work centers with capacity requirements were found

Former Member
0 Kudos

No work centers with capacity requirements were found

Message no. MD305

Diagnosis

The capacity situation is displayed for all work centers that are affected by the planned orders from the MRP list of the material.

System Response

If no capacity requirements are created when scheduling the corresonding planned orders, no capacity situation is displayed.

Procedure

Check whether capacity requirements are created when scheduling planned orders. Capacity requirements are not created, for example, if the planned order was scheduled using the data in the material master record or if you switched off the creation of capacity requirements in customizing.

Accepted Solutions (0)

Answers (3)

Answers (3)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

1) work scheduling view must be maintained.

2) Work center capacities with formulas must be relevent for "finite scheduling" and capacity planning.Chec in CO02 capacity view.

3) Controle key must have generate capacity reqs with scheduling indicator enable.

4) In planned order parameters OPU5 you must enable the indicator "generate capacity requirements with scheudling" with selection ID of routing.

While running MRP the scheduling mode must be 2 "lead time scheduling".

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

Check up with the foll. settings:

1. In spro , in scheduling parameters of planned orders and production orders (OPU5 and OPU3) "Generate Capacity requirements" check up is checked.

2. Check whether the capacity header details and formulas are maintained in the work center.

3. While MRP run, the MRP parameter for Scheduling "2 - Lead time scheduling & Capacity planning" is selected.

-Thaila Shree

Former Member
0 Kudos

Hi,

Pls put query in SD/MM forums.

Anil